Pictures 1-25 and the 1st video were taken on February 2, 2017.
The 2nd video was taken on July 26, 2021.
The 3rd video was taken on February 24, 2022.
Pictures 26-51 were taken on February 26, 2022.
The 4th video was taken on May 28, 2022.
Picture 52 was taken on March 27, 2023.
Picture 53 was taken on April 4, 2023.
Pictures 54-59 and the 5th video were taken on April 5, 2023.
Pictures 60-69 were taken on April 28, 2023.
The 6th video was taken on May 4, 2023.
Pictures 70-79 and the 7th video were taken on May 16, 2023.
Pictures 80-81 were taken on May 31, 2023.
Pictures 82-93 were taken on June 13, 2023.
The 8th video was taken on July 2, 2023.
All pictures and videos were taken by Tommy McGowan.
This crossing is located on the BNSF Mendota Sub.
1
2
Overview of 2 older gated signals facing north
Overview facing south.
3
4
5
6
7
8
9
10
11
The southern signal. This signal had a WCH base, two FS and two WCH frames, all 12"x20" with Dialight Ball LEDs, 4" RECO LEDs, and a Western Cullens Hayes Inc. gate mechanism.
12
13
14
15
16
17
18
19
20
21
The northern signal. This had similar parts, except it had a WRRS base, all FS frames, and a GS Type 1 E-Bell.
In February 2022, BNSF replaced the WCH signals with brand new Siemens signals. However, the way the did this was weird. They installed them on the existing foundations, carried over the GS Type 1 E-Bell and added a GS Type 3 to the southern signal, the southern signal's wind guard was also carried over, and the same relay bungalow was reused.
26
27
Overview of the new signals facing north
Overview facing south.
28
29
30
31
32
33
34
35
36
37
The new southern signal.
38
39
40
41
42
43
44
45
46
47
The new northern signal.
48
49
50
51
The same relay bungalow in the southwest quadrant.
In early 2023, work was starting to further modernize this crossing.
52
On March 27th, I spotted a new bungalow for this crossing in town, along with one for 300 E. St.
53
On April 4th, we see the bungalow for 300 E. St. was moved out to that crossing, but 450's was still here.
54
55
56
57
58
59
The very next day on April 5th, the new bungalow was moved out to the crossing. I wasn't sure at this point if these signals would be carried over or if even new signals would be installed, because the latter wouldn't really surprise me considering other crossings I've seen.
60
61
62
63
64
65
66
67
68
69
On April 28th, we see new foundations were installed and a large gravel mound was dropped off. I was confident at this point brand new signals were about to be installed.
70
71
72
73
74
75
76
77
78
79
On May 16th, we see the new foundations were already graveled in. By this point, I realized what BNSF was doing. The slits on the top of the foundations were facing parallel with the road, meaning the foundations were going to face forward. Normally BNSF installs new signals with bases facing to the right, but given these new signals were installed on old foundations, hence facing forward, this would be carried over to the new foundations, therefore, the current signals would be moved over.
80
81
By May 31st, the signals were moved to the new foundations, and on this day, the old bungalow was removed. Given the rural area, I didn't want to sit too long and look like I was stalking the workers.
82
83
84
85
86
87
88
89
90
91
92
93
By June 13th, the old foundations were removed, and further gravel was added around the new signals, thus finishing the completed setup.