![]() |
![]() |
![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() ![]() |
![]() ![]() ![]() |
| >>>>>>>>>>>>>> | Northern Signal | Southern Signal |
| Bell: | GS Type 3 E-Bell | GS Type 3 E-Bell |
| Cantilever: | Harmon Cantilever | Harmon Cantilever |
| Mast Base: | Siemens 5" Single Sided > | Siemens 5" Single Sided > |
| Lights: | 8 - 12"x20" Safetran w/ Dialight Ball LEDs 2 - 12"x24" Safetran w/ Dialight Ball LEDs |
8 - 12"x20" Safetran w/ Dialight Ball LEDs 2 - 12"x24" Safetran w/ Dialight Ball LEDs |
| Junction Boxes: | 2 Harmon, 2 Safetran | 2 Harmon, 2 Safetran |
| Gate Lights: | 4" RECO LEDs | 4" RECO LEDs |
| Gate Mechanism: | Siemens Imprinted w/ GSI Gate Saver | Siemens Imprinted w/ GSI Gate Saver |
| Gate Striping: | Vertical Striping | Vertical Striping |
| >>>>>>>>>>>>>> | Northwestern Pedestrian Gate | Northeastern Pedestrian Gate | Southwestern Pedestrian Gate | Southeastern Pedestrian Gate |
| Bell: | None | GS Type 3 E-Bell | GS Type 3 E-Bell | None |
| Base: | Siemens 5" Single Sided > | Siemens 5" Single Sided < | Siemens 5" Single Sided < | Siemens 5" Single Sided > |
| Gate Light: | 4" RECO LED | 4" RECO LED | 4" RECO LED | 4" RECO LED |
| Gate Mechanism: | Siemens Imprinted | Siemens Imprinted | Siemens Imprinted | Siemens Imprinted |
| Gate Striping: | Vertical Striping | Vertical Striping | Vertical Striping | Vertical Striping |
1![]() |
2![]() |
| Overview of 2 gated cantilevers and 2 pedestrian gate looking north. |
Overview facing south. |
3![]() | 4![]() | 5![]() | 6![]() |
7![]() | 8![]() | 9![]() | 10![]() |
11![]() | 12![]() | 13![]() | 14![]() |
| The southern signal. |
15![]() | 16![]() | 17![]() |
18![]() | 19![]() | 20![]() |
21![]() |
22![]() |
23![]() |
24![]() | 25![]() | 26![]() | 27![]() |
| The northern signal. |
28![]() | 29![]() | 30![]() | 31![]() |
| The northern pedestrain gate. |
32![]() | 33![]() |
34![]() | 35![]() | 36![]() |
| The southern pedestrian gate. |
37![]() | 38![]() |
| The relay bungalow in the southwest quadrant. | The grade is full concrete. |
39![]() | 40![]() | 41![]() |
| Track view facing west towards Railroad Ave. | Track view looking east towards Euclid Ave. | A CB&Q caboose at the Princeton Amtrak station. |
| 42 | 43 |
| Overview of the updated setup facing north. |
Overview facing south. |
| 44 | 45 | 46 |
| 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 |
| 55 | 56 | 57 | 58 |
| The southern signal. Both signals have Harmon cantilevers and WCH gate masts. The cantilever lights are 12"x20" Safetran frames with Dialight Ball LEDs and the mast lights are FS frames also with Dialight LEDs. the E-Bells were both GS Type 2 E-Bells. This signal still had a WCH gate mechanism. |
| 59 | 60 | 61 | 62 |
| 63 | 64 | 65 | 66 |
| 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| The northern signal. This signal had its WCH gate mechanism replaced in the early 2000s with a US&S Model 95 after the signal was moved closer to the mainline. Before, there used to be a side track on the north side of the crossing. Click here to see the old setup. |
| 76 | 77 | 78 | 79 |
| The southern pedestrian gate. This had a US&S base and US&S Model 95 gate mechanism with a 4" RECO LED. This was installed in the early 2000s and surprisingly didn't replace anything. |
| 80 | 81 | 82 | 83 |
| The northern pedestrian gate. This had a WRRS base and a WCH gate mechanism with no gate light. This was also installed in the early 2000s replacing a FS Company pedestrian gate. The WCH gate mechanism may have been the one off the old northern signal. Not sure why BNSF didn't go with a full US&S Model 95 setup. |
| 84 | 85 | 86 | 87 |
| The relay bungalow in the southwest quadrant. |
The grade is all concrete. |
Track view facing west towards Railroad Ave. | Track view looking east towards Euclid Ave. |
| 88 |
| In April 2023, a new bungalow was seen sitting off to the side, a sign of things to come. |
| 89 |
90 |
| 91 |
92 |
93 |
| 94 |
95 |
96 |
| 97 |
98 |
99 |
| 100 |
101 |
102 |
| 103 |
104 |
105 |
| 106 |
107 |
108 |
109 |
| 110 |
111 |
112 |
113 |
| In May 2023, we see most of the gates were restriped, the only exception being the rear of the pedestrian gate mounted on the northern signal. But things were about to change. |
| 114 |
115 |
116 |
117 |
| 118 |
119 |
120 |
121 |
| 122 |
123 |
124 |
125 |
| 126 |
127 |
128 |
129 |
| 130 |
131 |
132 |
133 |
| 134 |
135 |
136 |
137 |
| 138 |
139 |
140 |
141 |
| 142 |
143 |
144 |
145 |
| 146 |
147 |
148 |
149 |
| We see work was underway to replace the signals here. As of May 8th, the new road gate masts and two of the pedestrian gates were at the ready. The road masts had crossbucks and DOT tags install already which made me wonder if the cantilevers were being removed. |
| 150 |
151 |
| 152 |
153 |
154 |
155 |
| 156 |
157 |
158 |
159 |
| 160 |
161 |
162 |
163 |
| 164 |
165 |
166 |
167 |
| On May 22nd, we see the foundations for the pedestrian gates were moved next to where they'd be installed at. By this point too, the other 2 pedestrian gates were seen sitting at the ready. I was surprised to see these had bells on them, meaning they were going to make this a 4 bell crossing. |
| 168 |
169 |
170 |
171 |
| 172 |
173 |
174 |
175 |
| 176 |
177 |
178 |
179 |
| 180 |
181 |
182 |
183 |
| On June 5th, we see the foundations for the new pedestrian gates were installed in place. |
| 184 |
185 |
186 |
187 |
| On June 13th, we see all of the gates were lined up in a row waiting for install. Two lights were also installed on the road signal masts, indicating that cantilevers will be used with the new setup. I wasn't sure at this point if the old cantilevers were gonna be reused for if new ones were going to be installed. |
| 188 |
| As of June 16th, nothing had changed. |
| 189 |
190 |
191 |
| 192 |
193 |
194 |
| On June 28th, we see the new pedestrian gates were laying off to the side next to where they'd be installed. The next day, they'd be installed replacing the old pedestrian gates. |
| 195 |
196 |
| Overview of the in between setup facing north. |
Overview facing south. |
| 197 |
198 |
199 |
200 |
| The northwestern pedestrian gate. |
| 201 |
202 |
203 |
204 |
205 |
| The northeastern pedestrian gate. The old pedestrian gate was cut from the base and the base was left in place for now. |
| 206 |
207 |
208 |
209 |
210 |
| The southwestern pedestrian gate. |
| 211 |
212 |
213 |
214 |
| The southeastern pedestrian gate. |
| 215 |
216 |
217 |
218 |
219 |
| 220 |
221 |
222 |
223 |
| At the same time, the pedestrian gates that were mounted on the road signals were removed. This setup wouldn't last too long. |
| 224 |
225 |
226 |
227 |
| 228 |
229 |
230 |
231 |
| 232 |
233 |
234 |
235 |
| Additional views of the progress. |
| 236 |
237 |
238 |
| 239 |
240 |
241 |
242 |
| The old signals were sitting next to the Amtrak station, and we see the new road signals still sitting waiting for install. |
| 243 |
244 |
| Overview of the finished setup facing north. |
Overview facing south. |
| 245 |
246 |
247 |
| 248 |
249 |
250 |
| 251 |
252 |
253 |
| The updated southern signal. |
| 254 |
255 |
256 |
| 257 |
258 |
259 |
| 260 |
261 |
262 |
263 |
| The updated northern signal. |
| 264 |
265 |
266 |
| 267 |
268 |
269 |
| 270 |
271 |
272 |
| 273 |
274 |
275 |
| The old pedestrian gate bases were removed and the foundations were graveled in. |
| 276 |
| The new relay bungalow all by itself. |
| 277 |
278 |
279 |
280 |
| 281 |
282 |
283 |
284 |
| Additional pictures of the finished setup. |
| 285 |
286 |
287 |
| 288 |
289 |
290 |
| 291 |
292 |
293 |
| The old signals and relay bungalow were sitting off to the side next to the Amtrak station. You can also see the new crossbucks that were on the gate masts that were removed prior to install. Also, the new DOT tags that were on the gate masts were not used either. Very strange to see. |