MP: 116.01

Updated August 2024

Total Accidents:  1
Crossing DOT #:  175190P
TOTAL DAILY TRAINS:  54   (AS OF 2017)

>>>>>>>>>>>>>> Northern Signal Southern Signal
Bell: None GS Type 2 E-Bell
Base: WCH 5" Single Sided ^ WCH 5" Single Sided ^
Lights: 4 - 12"x24" Safetran w/ Electro-Tech's LEDs 4 - 12"x24" Hawker Safetran w/ Electro-Tech's LEDs
Junction Box: Safetran Safetran
Gate Lights: 2 - 4" RECO LEDs
1 - 4" NEG LED
3 - 4" RECO LEDs
Gate Mechanism: Safetran 1990s w/ GSI Gate Saver Safetran 1990s w/ GSI Gate Saver
Gate Striping: Vertical Striping Vertical Striping

Pictures 1-25 were taken on May 6, 2020.
Pictures 26-31 and the 1st video were taken on June 11, 2020.
Picture 32 was taken on October 7, 2020.
Pictures 33-36 were taken on January 5, 2021.
The 2nd video was taken on August 13, 2021.
The 3rd video was taken on September 14, 2021.
The 4th video was taken on May 19, 2022.
The 5th video was taken on November 9, 2022.
Pictures 37-38 were taken on February 8, 2023.
Pictures 39-46 were taken on December 5, 2023.
All pictures and videos were taken by Tommy McGowan.
This crossing is located on the UP Geneva Sub.

1
2
Overview of two 90s signals facing south. Overview facing north.
3 4 5
6 7 8
9 10 11
The northern signal.
12 13 14
15 16 17
18 19 20 21
The southern signal. Back in the early 2010s, the gates here had Electro-Tech's gate LEDs, one of the very few UP crossings in IL to have them.
22 23 24 25
The relay bungalow in the southwest quadrant. The grade is all concrete. Track view facing west towards Round Grove Rd. #1 in Morrison. Track view facing east towards Agnew Rd.
26 27
28 29 30 31
In June 2020, we see conduit was installed around the crossing in preparation for new signals to be installed here.
32
In October 2020, we see a new bungalow for this crossing sitting in Sterling.
33 34 35 36
In January 2021, we see the new bungalow was installed behind the current one. As of June 22nd, no more progress has been made yet.
37 38
2 years later in February 2023, the only thing that has changed was a PTC antenna was added to the new bungalow. No new signals, foundations, nothing.
39 40
41 42 43
44 45 46
In December 2023, something else did finally happen, but it was just that the DOT tags were turned forward. As of October 2026, work still hasn't progressed here, although crossings around Morrison are actively being worked on.