100.06


079676E

>>>>>>>>>>>>>> Western Signal Eastern Signal
Bell: GS Type 3 E-Bell GS Type 3 E-Bell
Base: Siemens 5" Single Sided > Siemens 5" Single Sided >
Lights: 4 - 12"x24" Safetran w/ Dialight Ball LEDs 4 - 12"x24" Safetran w/ Dialight Ball LEDs
Junction Box: Safetran Safetran
Gate Lights: 4" RECO LEDs 4" RECO LEDs
Gate Mechanism: Siemens Imprinted w/ GSI Gate Saver Siemens Imprinted w/ GSI Gate Saver
Gate Striping: Vertical Striping Vertical Striping

All pictures and the 1st video were taken on February 2, 2017.
The 2nd video was taken on December 13, 2021.
Pictures 26-29 were taken on March 29, 2023.
Pictures 30-41 and the 3rd video were taken on April 5, 2023.
Pictures 42-76 and the 4th video were taken on May 8, 2023.
Pictures 77-82 were taken on May 22, 2023.
All pictures and videos were taken by Tommy McGowan.
This crossing is located on the BNSF Mendota Sub.

1
2
Overview of 2 gated signals facing north.
Overview facing south.
3 4 5
6 7 8
9 10 11
The southern signal. Both signals have US&S gate mechanisms and 12"x20" FS frames with Dialight Ball LEDs.
12 13 14
15 16 17
18 19 20
21
The northern signal. This signal had a GS Type 1 E-Bell at the time. This was replaced by a GS Type 2 by late 2021. Also one of the LEDs was a General Signals LED.
22 23 24 25
The relay bungalow in the southwest quadrant.
The grade is all concrete.
Track view facing west towards Co. Rd. 1800 N.
Track view facing east towards Cherry St.
26 27 28 29
In March 2023, we see a huge gravel pile next to the crossing. A little later, I discovered a new bungalow for this crossing sitting in Zearing, a sign of things to come.
30 31 32 33
34 35 36 37
38 39 40 41
On April 5th, I got some closeup action shots of the crossing while this manifest was sitting on the crossing. You can see by this point the 1 General Signals LED was replaced by a Dialight Ball LED by this point.

In early May 2023, brand new signals were installed at this crossing.

42
43
Overview of the new gated signals facing north.
Overview facing south.
44 45 46
47 48 49 50
51 52 53 54
The new southern signal.
55 56 57
58 59 60 61
62 63 64 65
The new northern signal.
66 67 68 69
The new relay bungalow in the northeast quadrant.
The grade is all concrete.
Track view facing west towards Co. Rd. 1800 N.
Track view facing east towards Cherry St.
70
The old relay bungalow was still in place at this point.
71 72 73 74
This really confused me, as this was the first time I had seen a base be left in place. Not only that, but a new piece of conduit was installed off the side of it. I had thought BNSF was gonna leave this in for quite a while seeing what was done to it.
75
76
One more view of the crossing, plus one of the work vehicles had a flat tire.
77
78
79 80 81 82
On May 22nd, we see the old bungalow was removed, the foundations were graveled in, and the old base was removed. I have no idea why BNSF installed new conduit to it if they were just gonna remove it so soon.